Answer :
Answer:
MCE = 1/3 = 33.33%
Explanation:
[tex]\frac{Value \: Added }{Manufacturing \: Cycle \: time} = MCE[/tex]
Value added acivities:
Throughput time 4.4 hours --> value added
Process time 1.1 hour --> value added
total time ading value 5.5 hours
total hours of the cycle
4.4 + 8.8 + 1.1 + 2.2 = 16.5 total time
MCE = 5.5/16.5 = 1/3 = 33.33%