Answer :
Answer: The answer is $1,080,000
Explanation :
Step one :
Since the said approved amount is
$1,200,000 and it is subject to 10% retention
10%of $1,200,000=
10/100*$1,200,000=$120,000
Step two:
The amount that should be debited to Construction Expenditures is approved amount
$1,200,000 minus 10% retention amount
$1,200,000-$120,000
$1,080,000
Answer:
$1,080,000
Explanation:
Progress billing submitted on the construction contract = $1,200,000
If the bill was approved to 10% retention, the retention amount will be 10% of $1,200,000
Retention amount = 10/100×$1,200,000
Retention amount = $120,000
Amount debited to construction expenditure = Initial billing - retention amount
Amount debited to construction expenditure = $1,200,000 - $120,000
Amount debited to construction expenditure = $1,080,000