Answer :
Answer:
The correct option is C,$40,956
Explanation:
NPV=present value annual cost savings-initial investment
NPV is -$1800
present value of annual savings=$20,000/(1+12%)^1+$16,000/(1+12%)^2+$12,000/(1+12%)^3=$39,153.61
-$1800= $39,153.61 -initial investment
initial investment=$ 39,153.61+$1800=$40953.61
The correct option is the option C,$40,956 which is closest to $40953.61 ,the difference arose from rounding errors when the discount factors were rounded to to three decimal places instead of using the exact figures