Answer :
Since the crossover point is 11.4 percent and have decided to accept project X because the required return is 12.7 percent, it that implies that we sould always accept Project X if the required return exceeds the crossover rate.
Crossover rate refers to the cost of capital where the net present values of 2 projects are equal.
- After the cross over rate, the project X will remain better compared to project Y.
- Hence, since the crossover point is 11.4 percent and have decided to accept project X because the required return is 12.7 percent, it implies that we should always accept Project X if the required return exceeds the crossover rate.
Therefore, the Option C is correct.
Missing options "A. accept Project Z if the required return is less than 12.7 percent. B. be indifferent to the projects at any discount rate above 12.7 percent. C. always accept Project X if the required return exceeds the crossover rate. D. always accept Project X E. accept Project Z only when the required return is equal to the crossover rate."
Read more about crossover rate