Answer :
The number of workers required to meet the labor demand of 800hr/wk is 20.
Data;
- Regular rate = $15.0/hr
- Overtime rate = $22.50/hr
- Labor hours needed = 800/wk
- Any hour above 40 hours = overtime
Number of Workers Required to meet labor cost
The number of workers need to meet the labor cost can be calculated as
[tex]\frac{800}{40} = 20[/tex]
The number of workers required to meet the labor demand of 800hr/wk is 20.