myOMLab Homework 5 Project Management Activity A B C D E Recently, you were assigned to manage a project for your company. You have constructed a network diagram depicting the various activities in the project (shown below to the right). In addition, you have asked your team to estimate t they would expect each of the activities to take. Their responses are shown in the following table: Optimistic 6 4 5 1 4 Time Estimates (days) Most Likely Question 5, Problem 21 Part 2 of 3 a. What is the expected completion time of the project? The expected completion time is 20 days. (Enter your response as an integer.) b. What is the probability of completing the project in 22 days? Refer to the standard normal table. The probability of completing the project in 22 days is 7 6 5 8 (Enter your response rounded to four decimal places.) Pessimistic 12 11 8 6 11 > Start HW Score: 80%, 8 of 10 points O Points: 0 of 2 Finish OU